" Do you want to provide children in the community with a safe, rewarding and environmentally friendly play space through a recycled playground model with Think Playgrounds? How wonderful! Here are 5 steps to turn your ideas into reality:" - Chu Kim Duc - Co-founder - CEO
Survey and design activities with the community: 3 - 5 days Playground construction: 5-10 days Capacity building training for the community: 3-5 days Exchange and communication activities: 1 day/week
Collect information and survey the site according to the form and work with the local government and community to ensure the legality of land use and the consent of the local community
Think Playgrounds experts will prepare and host design meetings with the community. Please ensure the participation of community representatives including children, youth, women, the elderly, people with disabilities (if any)... to collect a variety of opinions.
The final design is sent to the locality for approval to be ready for construction with community participation
Construction activities will have the participation and supervision of the local community. Activities to complete the playground installation will invite the community to participate such as painting, planting trees...
After completing the playground, a group of local community representatives are invited to participate in maintenance training to jointly develop a plan to manage, use and maintain the playground. The parties can organize handover and opening events of the playground with creative fun activities for children.